Bio mining at Wariyana Dump

Components/Scope of Work:

• 8 Lakh MT legacy waste to be processed

Total time period-32 months

(6- month-installation & 26 month processing time period after contract signed

Per Day Processing capacity: 1500Ton/day @ 60 ton per hr

 

Project Cost (Cr.):

38.63 Cr.

Project Time Period:

32 Months

Mode of Implementation:

Tender

Implementing Agency:

M/s Sagar Motors

Present Status:

Work in Progress

Benefits of project:

Legacy Waste Clearance: Reclaims land by processing old dumps

Pollution Reduction: Cuts air, soil, and groundwater contamination

Public Health Protection: Reduces biohazards for nearby residents

Environmental Restoration: Improves overall ecosystem quality

Odour & Fire Control: Minimizes foul smell and landfill fire risks

Resource Recovery: Enables reuse of materials and land redevelopment.